3D model predicts seabed recovery following dredging
Offshore cables form the backbone of our offshore energy and data infrastructure, but seabed dynamics can expose them. To prevent this, additional dredging may be required before cable installation, partly due to shifting sand waves. New 3D simulations show which processes determine how and how quickly a dredged cable trench fills in. This enables offshore operations to be planned more effectively and risks to cable infrastructure to be minimised.
Sand waves pose a risk to offshore infrastructure
Shallow, sandy seabeds are vital for the energy transition, for instance for offshore wind farms and subsea power and data links. It is precisely in these areas that sand waves, also known as marine dunes, often occur: large, dynamic seabed features that can migrate and, over the course of years, cause differences in seabed elevation of several metres. This can pose risks to cables, for example if a cable becomes exposed.
For this reason, the seabed is regularly dredged before cables are installed. Dredging makes it possible to lay the cable below the trough level of the sand wave. The machinery used for this often cannot reach deep enough, so the sand must be removed first. If the cable is laid deep enough, it will not be exposed when a sand wave slowly passes by.
Predicting the infilling of a cable trench is a complex problem, but it is very important for protecting cables from exposure, reducing their visibility to prevent sabotage, and restoring the ecosystem.
Pauline Overes, a researcher in coastal and seabed dynamics at Deltares and the University of Twente, explains further: “Dredging allows a cable to be laid below the lowest point of a sand wave, ensuring it remains protected even as sand waves shift. The sand waves then usually grow back and form a natural protective layer. At the same time, that layer must not become too thick, as this would reduce the cable’s ability to dissipate heat and could cause it to overheat. The 3D model allows a trench to be designed efficiently so that it remains open long enough for the cable to be laid, but then fills in naturally afterwards. This minimises dredging work, reduces costs and minimises the environmental impact.”
You have not yet indicated whether you want to accept or reject cookies. This means that this element cannot be displayed.
Or go directly to:
From measurements to predictive process understanding
Existing, data-driven prediction methods work well under natural circumstances, as long as the system is not significantly disrupted. After dredging, however, the situation is different: the existing seabed dynamics are disrupted and commonly few measurements are available, as areas where cables are laid (such as offshore wind farms) are frequently closed off to public measurements following these activities.
That is why a process-based 3D model was used in this research, using the Delft3D Flexible Mesh (FM) software developed by Deltares. The researchers modelled a cable trench approximately 20 metres wide that was dredged in 2018 through a field of sand waves for the NEMO Link power cable between Belgium and the United Kingdom. Available seabed measurements spanning several years made it possible to compare the model results with the actual development of the seabed.
Through this research, we provide greater insight into the complex 3D processes involved in the recovery of a cable trench in a sand wave area and how these, together with the trench design, influence the rate of infilling. That insight, and our new modelling knowledge, help to improve the planning of offshore operations and minimise risks to cable infrastructure.
Pauline Overes, researcher in coastal and seabed dynamics, Deltares / University of Twente
New process knowledge can improve design
The models can answer many questions from cable operators and developers, such as: How long does a dredged cable trench remain open? And will the sediment return naturally to act as a buffer against future risks? The simulations show that, after dredging, sand slides into the trench mainly from the sides. This happens most rapidly in places where the adjacent sand waves are high and steep. As a result, the trench does not fill in at the same rate everywhere. At the same time, interactions between the adjacent sand waves and tidal currents cause the sand within the trench to be dispersed further. In this way, the sand waves in the trench slowly grow back.
The timing of the dredging works also makes a difference. Around spring tides, the currents are stronger and can displace more sand than around neap tides. This means that a trench can fill in more quickly if strong tidal currents occur shortly after dredging. In the situation studied, a storm did not cause much additional infill overall, but it did lead to more infill on one side of the channel. This is relevant for planning cable installation: the centre of the trench, where the cable is often installed, is not always exactly the spot where sufficient space remains for the longest time.
The research also highlights which design choices help to mitigate risks. A wider trench keeps the sand away from the centre for longer, but also requires more dredging work. A gentler side slope ensures that the trench infill rates are reduced. In the model results, adjusting the side slope had a greater impact on the infilling rate than simply widening the trench. Such insights help to strike a better balance between dredging volume, installation time and cable protection, and ultimately reduce both costs and environmental impact.

Unique model
Given the complexity of the system and the need for high resolution in the model, this is the first time a cable trench in a sand wave field has been modelled in 3D.
Using Delft3D FM, it was possible to simulate the multi-year recovery process; furthermore, the model proved capable of accurately simulating the sediment balance without the need for calibration. This demonstrates that the Delft3D FM model developed by Deltares is highly suitable for gaining a better understanding of these complex cases.
The research was carried out by researchers from the University of Twente, Deltares and Delft University of Technology, with support from the Dutch Ministry of Economic Affairs and Climate Policy via the SITO-IS grant and from NWO via the Footprint project. Bathymetric data from the Agency for Maritime Services and the Coast were also used.